HomeMy WebLinkAbout2021-11-30 2:00PM WORKSHOP SESSIONBRAZOS COUNTY
B RYAN, T EXAS
NOTICE OF MEETING AND AGENDA
WORKSHOP SESSION
BRAZOS COUNTY COMMISSIONERS COURT
FILED
t
2021 NOV 24 A f!= 2s
ll i; ' `` IMMIX u. r
0311
a.
BRAZOS COUNTY COMMISSIONERS WILL MEET IN A WORKSHOP SESSION AS FOLLOWS:
MEETING DATE: November 30, 2021
MEETING TIME: 2:00 PM
MEETING PLACE: Brazos County Administration Building, 200 South Texas
Avenue, Suite 339, Bryan, TX
1. Call to Order
2. Discussion of planning for future road projects.
3. Adjourn
The Brazos County Administration Building, 200 South Texas Avenue, Suite 339, Bryan, TX is wheelchair accessible. Handicap
parking spaces are available. Any request for sign interpretive services must be made two working days before the meeting.
To make arrangements, please call (979) 361-4102.
Vol. J -n' PB' ��5
MINUTES
NOVEMBER 30, 2021
BRAZOS COUNTY COMMISSIONERS COURT
WORKSHOP SESSION
Call to Order
The Commissioners' Court of Brazos County, Texas met in a Workshop Session in
Room 339 in the Brazos County Administration Building in Bryan, Brazos County, Texas
beginning at 2:00 p.m. on Tuesday, November 30, 2021 with the following members of
the Court present:
Duane Peters, County Judge, Presiding;
Steve Aldrich, Commissioner of Precinct 1;
Russ Ford, Commissioner of Precinct 2;
Nancy Berry, Commissioner of Precinct 3;
Irma Cauley, Commissioner of Precinct 4;
Karen McQueen, County Clerk, Absent.
The attached sheet contains the names of those in attendance.
2. Discussion of planning for future road projects.
Judge Peters asked John Polster with Innovative Transportation Solutions, Inc. to begin
his presentation. Mr. Polster gave an overview on the Road Planning and Programming
Process for State and Local Roadways and the potential Road Bond Program.
Commissioner Aldrich stated that integration between the RMA and MPO is crucial. He
said infrastructure is his highest priority and feels the Court should move forward.
Commissioner Berry agreed with Commissioner Aldrich. Judge Peters also stated that
transportation issues are growing and should be addressed now. Mr. Polster said he
would like to start meeting with the Court members to find out the concerns for each
precinct and the county as a whole.
There being no further business to discuss, the meeting was adjourned. A copy of the
Vol.._�Pg.
presentation is attached.
Adjourn
Vol-_J� P9. I��
The foregoing minutes of the Commissioners Court Workshop Session held November
30, 2021 have been examined and are approved in open Court this the 7th day of
December 2021, in Bryan, Brazos County, Texas.
Duane Peters
County Judge
Russ Ford
Commissioner, Precinct 2
Irma Cauley
Commissioner, Precinct 4
Attest:
c
Karen McQueen
County Clerk
G�
Steve Aldrich
Commissioner, Precinct 1
4 M
ZE
LIN I 814MB . _ ,;1
Commissioner, Precinct 3
Pg I of I
BRAZO S COUNTY
COMMISSIONER'S COURT
DAY OF 24 a -I
-AMC45
Name
(PLEASE PRINT)
Organization
(PLEASE PRINT)
K I W64,
1 II
BUILDING ROADS IN TEXAS:
FROM NEED TO CONSTRUCTION
AN OVERVIEW
OF THE
PLANNING AND PROGRAMMING PROCESS
FOR
STATE AND LOCAL ROADWAYS
Prepared for:
Brazos County, Texas
Prepared 1)�:
Innovative Transportation Solutions, Inc.
Brazos County Workshop
Transportation Planning and Programming
November 30, 2021
Agenda
1.) TxDOT Project Delivery Process
2.) TxDOTBCSMPO Concurrence Process
3.) Brazos County RMA
4.) Brazos County Opportunities
5.) Potential Road Bond Program
6.) Questions?
0
04
TxDOT Project Selection Process
Needy
A Need is
Identified
Every project starts
with an idea or need.
Once a need has
been identified,
project supporters
usually approach
TxDOT's local
district office or their
local (MPO).
°Consider
:Funding
Building a
Successful Proposal
At the local level, the
public and TxDOT
evaluate the project and
work together to gain
funding and support.
Early in the planning
process, the district staff
devises a funding
strategy for the
suggested project. The
availability of funding is
a major factor in
determining whether a
project is selected.
Planning'.; y Develop
Begins ' Project..
Planning Begins
Once supported by
TxDOT or by MPO, it
competes with similar
projects for funding.
Project selection
authority rests with TTC
and local officials. Most
of TxDOT's budget
funds projects in the
UTP. In evaluating which
projects will receive
money, TTC takes into
account local support
and local funds have
been set aside to aid in
the project's completion.
Project Development
Once authorized, a
project goes through a
development phase that
includes advanced &
environmental planning
and documentation &
preliminary engineering.
When completed, the
project must go through
contract approval & the
TTC makes the final
decision authorizing
construction, based on
the availability of funds
and local priorities.
Build It
This strategy oversees
construction projects
that add capacity to the
state's transportation
system, either through
new projects or those
which supplement the
existing infrastructure.
TEXAS DEPARTMENT OF TRANSPORTATION METROPOLITAN PLANNING ORGANIZATION
Each District Updated every three
stibmits projects for years by MPO. Input
possible inclusion on from member cities
UTP. and MPO staff.
'Preventative Maintenance &
Rehabilitation
Structures Replacement &
Rehabilitation
Metropolitan Area Corridor
Projects'
Urban Area Projects
Statewide Connectivity
Corridor. Projects
Congestion Mitigation i£ Air
Quality Improvements
Metropolitan .
Mobility/Rehabilitation
STP Safety
Transportation
Enhancements
Miscellaneous
District Discretionary
Strategic Priority
Unified Van'. Plan MOBILITY 2025
10 year, plan �_ Long-range plan
updated annuallyconcurrent updated every three
years -
TxDOT portion of MPO portion of three STBG Funds
three year year Transportation
> Transportation Plan �— Congestion Mitigation
Improvement Plan (if in a Non -
Attainment area)
Each region's TIP is put together to become
the STIP after approval by the Texas
Transportation Commission -
State Transportation Improvement
- Program
Vol. 3�{� pg. tA_/
Locally Funded
. Projects
Unified Planning
Work Program
MPO work plan
WHAT IS A REGIONAL MOBILITY
AUTHORITY?
The Brazos County Regional Mobility Authority (BCRMA) is a countywide
independent local government agency. It is a regionally focused transportation and
implementation entity intended to enhance the transportation network. It is locally
controlled, but unlike a city or county it has no taxing authority. The creation of an
RMA is allowed by Texas Statute and must be authorized by the Texas
Transportation Commission. There are currently 10 RMAs in Texas.
The BCRMA has the capability to work in any mode of transportation. For
example, roads, aviation, transit, parking, bus and pedestrian facilities. The key
role of the BCRMA in our area will likely be to accelerate the development of
projects which have been determined in the local planning process. The RMA can
use its capabilities to bring different agencies and funding together to leverage
resources and expedite timelines.
Brazos County Opportunities
As has been shown from the previous information, there is significant effort put
into a project before it is funded and constructed. Those steps are required if a
project wishes to access federal or state funding.
Brazos County has the opportunity to impact its transportation needs more directly
by assisting its transportation partners with the early stages of project development
such as schematic approval, environmental clearance, design, ROW acquisition
and utility relocations.
While much of the funding for state facilities is allocated to the various districts
throughout the state, additional consideration is given to those projects that have
local support and local funding. This allows TxDOT to leverage their resources to
develop and construct more projects.
The amount of funding the state expects to expend over a ten year period is known
and is tentatively allocated to projects within each District. Those projects must
meet their anticipated let dates in order for the state to expend the funds in the
month they are allocated. Many times, projects miss their let dates and the state
must fill that "gap" with another project.
By Brazos County taking the initiative to fund the advanced planning for projects
critical to the needs of its citizens, it places itself in a position to access these "gap"
funds.
Potential Road Bond Program
One of the more traditional methods for procuring the necessary funds to address
the transportation. needs of Brazos County is through voter approved road bonds.
In order to make a detennination as to the viability of a road bond program, several
factors should be considered. The Brazos County Commissioners Court should
enlist the assistance of its financial advisors and bond council to determine the
amount of funds possible for a road bond, the impact to the tax rate, and the
structure of the bond covenants.
Those factors will better inform the Court as to the financial limits of the bond
program and its timing.
If the determination is made to move forward with a road bond program,
consideration should be given to such questions as:
1. Amount of the bond program
2.. Selection criteria of candidate projects that could include:
- Consistency with the Mobility Plan
- Leveraging potential
- Regional Significant/Multi-jurisdictional
- Safety
- Congestion Relief
- Economic Development potential.
3. Distribution of funds by Precinct
4. Input from Federal, State and Local partners
The selection process should be developed in a manner that meets the most needs
of the county while creating "buy in" from its partners.
F3 LA 8 Pg.
QUESTIONS?